c. ADJUSTMENT
Place boom on boom support (12). Loosen nut (7) and adjust latch adjusting screw (6) until support latch (1) is
fully engaged. Tighten nut.
NOTE
Follow-on
maintenance:
Lower hoisting boom (refer to TM 9-2350-256-10)
9-45 REPLACE TRANSMISSION GUIDE BARS
THIS TASK COVERS
a. Removal
b. Installation
INITIAL SET-UP
Tools:
Parts:
Equipment Condition.
Tool kit, general mechanics
Lockwashers (8) (Appendix G,
Engine deck removed (see
(Appendix C, item 53)
item 131)
paragraph 9-51)
a. REMOVAL
CAUTION
Remove only one guide bar at a time.
Remove two guide bars (1) by removing eight screws (2), eight lockwashers (3), four flat washers (4), and eight
nuts (5).
b. INSTALLATION
Install two guide bars (1) with four flat washers (4), eight new lockwashers (3), eight screws (2), and eight nuts (5).
NOTE
Follow-on maintenance:
Install engine deck (see paragraph 9-51)