Figure 3-24. Disassembly of Hoist Winch Assembly into Subassemblies.
c
Test. Before installing cable on winch, the wire rope assembly is to be tested to 17,400 lb prior to attaching
ferrule on winch end, with the clevis installed and the winch end clamped.
3-21
Assembly of Hoist Winch Assembly from Subassemblies
Assemble the hoist winch assembly in reverse order of disassembly (fig. 3-24).
3-21.1 Adjustment of Hoist Winch
Valves are adjusted by the vehicle manufacturer. Should verification need to be made, refer to paragraph 2-21 for
procedure.
a.
Deleted.
b.
Deleted.
c.
Deleted.
d.
Deleted.
3-21.2 Adjustment of Live Boom Capability
Refer to paragraph 2-22 for adjustment procedure.