QUARTERLY NOTES (CONTINUED)
Note 31
UNIVERSAL JOINTS
Note
Power plant does not need to be removed to
lubricate universal joints.
Lubricate all fittings with GAA. Wipe off extra lubricant.
A
Rotate drive shafts (1) and (2) until lubrication fittings are
accessible.
Lubricate fittings with GAA and wipe off excess.
B
C
Rotate turret to rearward position and remove stowage box.
Rotate pump drive shaft (3) until lubrication fittings are accessi-
ble. Lubricate fitting with GAA and wipe off excess.
Remove four screws (4) and disconnect pump drive shaft from
D
carrier bearing (5).
Remove Iockwire and four screws (6).
E
Note
Drive shaft will separate if extended too far. Ex-
tend only far enough to gain access to lubrication
fittings.
Pull carrier bearing (5) just far enough into turret well to gain
F
access to clutch-to-carrier bearing drive shaft lubrication fitting.
Lubricate fitting on universal joint with grease (GAA) and wipe
G
off excess.
Install carrier bearing and pump drive shaft.
H
I
C a r d 17 of 40
LO 9-2350-238-12