TM 9-2350-256-20-1
0084 00
CORRECTIVE ACTION Continued
voltage. Turn MASTER switch OFF. If voltage is present, repair/replace wire 10 of main lighting and
B.O. selector switch wiring harness (see WP 0218 00). If voltage is not present, go to step 11.
11. Reconnect switch panel to gage panel and miscellaneous switches wiring harness to main switch panel.
Open air inlet doors (TM 9-2350-256-10). Disconnect wire 48 pin A from bulkhead to master relay
wiring harness. Place red multimeter lead in socket and black lead to ground. Turn MASTER switch
on and check for voltage. If voltage is present, repair/replace switch panel, radio, and bilge pump to
bulkhead wiring harness (see WP 0202 00). If voltage is not present, troubleshoot master relay circuit
END OF WORK PACKAGE
0084 00-7/8 blank