TM 9-2350-256-34
0062 00
Assembly
NOTE
Refer to TM 5-725 for zinc filling methods.
1.
Install ferrule (7) and zinc filling to drum end of cable (6).
2.
Clamp cable (6) in vise with approximately 12 in. (30.5 cm) projecting up.
3.
Hammer sleeve (4) onto cable (6), and install tapered plug (5) with small end of plug pointing into center of cable. Place
a cable strand into each plug groove and drive plug into sleeve. Hammer cable strands down onto top of tapered plug and
install clevis (3).
4.
Install bolt (2) and nut (1) to clevis (3).
5.
Lubricate main winch cable in accordance with TM 9-2350-256-10.
Test and Inspection
1.
Before installing cable on winch, the wire rope assembly is to be tested to 17,800 lb (8074 kg) prior to attaching ferrule on
winch end, with the clevis installed and the winch end clamped.
Installation
1.
Install hoist winch cable in accordance with TM 9-2350-256-20.
END OF WORK PACKAGE
0062 00-3/4 blank