TM 9-2350-256-20-2
0419 00
Installation
1.
Install ID plates (50, 51, 52, and 53) with four drivescrews (54, 55, 56, and 57) each.
2.
Install elbows (47 and 48) to fuel transfer pump (49).
3.
Connect hoses (45 and 46) to elbows (47 and 48).
4.
Install two caps (43 and 44) and two couplings (41 and 42).
5.
Install two locknuts (39 and 40) and two elbows (36 and 38) to two couplings (41 and 42).
6.
Connect hose (37) to elbow (38), and hose (35) to elbow (36).
7.
Install tee (33) to regulating valve (34), and elbows (30 and 32) to tee.
8.
Connect hose (31) to elbow (32), and hose (29) to elbow (30).
9.
Install elbow (27) and locknut (28) to control valve (9).
10. Connect hose (26) to elbow (27), and install elbow to control valve (9).
11. Install pipe (24) to elbow (25) and tee (16).
12. Install locknut (23) and tee (20) to tee (16).
13. Install elbow (22) to tee (20) and hose (21).
14. Install locknut (19) and elbow (18) to tee (20), and hose (17) to elbow.
15. Install locknut (15) and elbow (14) to tee (16), and connect hose (13) to elbow.
16. Install locknut (12) and elbow (11) to control valve (9).
17. Connect hose (10) to elbow (11), and install locknut (8) and tee (4) to control valve (9).
18. Install locknut (7) and elbow (6) to tee (4).
19. Connect hose (5) to elbow (6), and install nipple (3) to tee (4).
0419 00-4