2.
Reconnect gage panel to bulkhead wiring harness to gage panel. Disconnect wire 27B from generator
indicator gage. Place red lead of multimeter in wire 27B and black lead to ground. Turn MASTER
switch on and check for voltage. Turn MASTER switch OFF. If voltage is present, replace generator
indicator gage (see WP 0157 00). If voltage is not present, repair/replace wire 27B from connector to
generator indicator gage of gage panel wiring harness (see WP 0193 00).
3.
Reconnect gage panel to bulkhead wiring harness to gage panel. Install ground strap (5), two lock-
washers (4), two screws (3), gage panel (6), three lockwashers (2), and three screws (1) to mounting
brackets.
Remove three screws (7), three lockwashers (8), ground wire (9), flat washer (10), and release main
switch panel (11) from mounting brackets. Disconnect switch panel to gage panel and miscellaneous
switches wiring harness from main switch panel. Place a jumper wire from pin N to socket N. Place