TM 9-2350-256-20
All personnel must stand clear during
lifting operations. A swinging or shifting
load may
cause injury or death to
personnel.
NOTE
Sling (69) is premarked to ensure proper
rigging for powerplant (70) removal.
30
Remove power-plant (70) from vehicle hull (71)
using sling (69).
31
Remove two preformed packings (72) from each
side of transmission saddle (73).
Do not step on shifting, steering, or brake linkages after removing powerplant. Damage to linkages
could result.
32 Install steering clutch housing output shaft parts kit (74). Cover ends of left and right output reduction
assemblies in hull with tape or other suitable item after removal of powerplant.
b. INSTALLATION
NOTE
Prior to installation, inspect and adjust fire extinguisher nozzles in engine compartment and check
that all powerplant lines, cables, accessories, and other components are properly installed,
tightened, and adjusted. Inspect transmission output reduction drives and engine mountings and
connections in engine compartment to determine if items are serviceable and positioned to receive
powerplant.
Clean (flush) engine compartment prior to installation of powerplant.
Prior to installation of powerplant, perform necessary engine compartment lubricating procedures
(refer to TM 9-2350-256-10).
Change 1
3-7