TM 9-2350-256-34
INTERMEDIATE MAINTENANCE
RECOVERY VEHICLE, FULL TRACKED: MEDIUM, M88A1
BILGE PUMP CIRCUIT BREAKER TO SWITCH PANEL LEAD ASSEMBLY MAINTENANCE
REMOVAL, REPAIR, INSTALLATION
INITIAL SETUP:
Materials/Parts (cont.)
Test Equipment
Tools and Special Tools
References
Equipment Condition
Materials/Parts
Master switch off
Battery ground cables disconnected (TM 9-2350-256-20)
Removal
1.
Remove screw (1) and disconnect bilge pump circuit breaker to switch panel lead assembly (2) from relay (3).
2.
Disconnect connector (4) and remove lead assembly (2).
Repair or Replacement
1.
Repair lead assembly as required in accordance with WP 0033 00.
Installation
1.
Connect connector (4) of lead assembly (2).
2.
Install lead assembly (2) and screw (1) to relay (3).
END OF WORK PACKAGE
0036 00-1/2 blank