TM 9-2350-256-34
0068 00
Testing
NOTE
LOAD TEST--Perform steps 1 thru 4 for the load test of the hoisting boom assembly.
NOTE
The following load test must be performed with the hydraulic reservoir oil temperature at 100 F130 F
(38 C54 C).
1.
Rig a four-part line and extend the boom to an 8-ft (2.44-m) reach.
2.
Attach load. Use load cell or calibrated weights if available. The rear of an M88A1, a medium tank, or equivalent may be
used if the load cell or weights are unavailable.
3.
Activate boom valve to RETRACT position.
4.
If vehicle fails to pass the load test, perform procedures as specified in ADJUSTMENT above.
END OF WORK PACKAGE
0068 00-9/10 blank