TM 9--2350--292--20--2
0672 00--1
SMOKE GRENADE LAUNCHER BRACKET REPLACEMENT
0672 00
THIS WORK PACKAGE COVERS:
Removal, Installation
INITIAL SETUP:
Tools and Special Tools
General mechanics tool kit (item 1, WP 0717 00)
Materials/Parts
Lockwashers (8) (item 85, WP 0718 00)
Lockwashers (2) (item 86, WP 0718 00)
Equipment Conditions
Smoke grenade arming switch box removed
(WP 0671 00)
Exhaust smoke switch and switch plate removed
(WP 0259 00)
Smoke grenade firing switch box removed
(TM 9--1040--267--20&P)
References
TM 9--1040--267--20&P
Removal
1. Remove four nuts (1), eight lockwashers (2) and four screws (3) from bracket (4). Discard lockwashers.
2. Remove two screws (5), two lockwashers (6) and bracket (4). Discard lockwashers.
3. Inspect parts for damage and replace as required.
Installation
1. Install bracket (4) with two screws (5) and two new lockwashers (6).
2. Install four screws (3), eight new lockwashers (2) and four nuts (1) on bracket (4).