TM 9--2350--292--20--2
HOIST WINCH WIRE ROPE SHIELD REPLACEMENT -- CONTINUED
0495 00
Installation--Continued
3. Position assembled shields (3, 7 and 8) and align with mounting holes.
4. Secure bottom shield (7) with nine screws (4), nine new lockwashers (5) and nine flat washers (6).
5. Secure top shield (3) with 10 screws (1) and 10 new lockwashers (2).
Figure 260
3
4
5
6
7
8
1
2
NOTE
FOLLOW--ON MAINTENANCE:
Install commanders seat (WP 0457 00)
Install hoist winch wire rope (WP 0493 00)
Install dome light (WP 0283 00)
Install liquid container brackets (WP 0474 00)
Install PTO/accessory panel (WP 0245 00)
Install passive night viewer stowage box assembly and
mounting bracket (WP 0468 00)
Install hand grenade boxes (WP 0466 00)
Install wiring harnesses 4W136, 4W153
and lead assembly 4W140 on hoist winch wire rope
shield (WP 0325 00, WP 0328 00 and WP 0326 00)
Install ceiling and bulkhead rifle clips (WP 0481 00)
END OF TASK
0495 00--3/4 blank