Installation
1. Install lubrication fitting (11) in shaft (5).
WARNING
2. Install two pulleys (10) on boom with three spacers (9) and shaft (5).
3. Install stayline cable (8) on shaft (5) with flat washer (3), nut (7) and new self--locking nut (6).
4. Install stayline cable (4) on shaft (5) with flat washer (3), nut (2) and new cotter pin (1).
5. Lubricate shaft (5) through lubrication fitting (11) (WP 0187 00).
Figure 282
1
2
3
4
5
7
8
11
6
9
10
9
10
9
3
NOTE
FOLLOW--ON MAINTENANCE:
Rig boom (TM 9--2350--292--10)
END OF TASK